LGE-KU-LGE-GIS-2019-004
200 MW hybrid in Breckinridge, KY · In queue since February 2019 · Proposed COD December 2022
200 MW
Capacity
1
Components
Solar
7y 3m
In Queue
Suspended
IA Status
COD target: 2022
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
The proposed project LGE-KU-LGE-GIS-2019-004 is a 200 MW solar and battery hybrid development located in Breckinridge County, Kentucky. The project consists of 200 MW of solar generation paired with battery storage. It is being proposed by Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU).
The project entered the LGE-KU interconnection queue on February 7, 2019, with a proposed commercial operation date of December 1, 2022. Interconnection service is to the Hardinsburg 138 kV Substation. The project's interconnection agreement status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
KY
County
Breckinridge
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Hardinsburg 138 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.