LGE-KU-LGE-GIS-2021-007
120 MW generation in Mccracken, KY · In queue since March 2021 · Proposed COD June 2026
120 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-15
LGE-KU-LGE-GIS-2021-007 is a proposed solar generation project with a total capacity of 120 MW. It is located in Mccracken County, Kentucky, within the service territory of Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). The project entered the LGE-KU interconnection queue on March 22, 2021, with a proposed commercial operation date of June 15, 2026.
The interconnection agreement (IA) status for the project is currently listed as "Suspended". The point of interconnection (POI) is the Grahamville 161 kV bus, with an alternate POI at the Grahamville to Wickliffe 161 kV line. The queue status is also listed as "suspended".
Generated from interconnection queue and public data sources
State
KY
County
Mccracken
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Primary: Grahamville 161 kV bus ; Alternate: Grahamville _x0013_ Wickliffe 161 kV line, SIS Primary changed to : Grahamville 161 kV bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.