LGE-KU-LGE-GIS-2021-008
500 MW hybrid in Clark, IN · In queue since March 2021 · Proposed COD June 2026
500 MW
Capacity
1
Components
Solar
5y 2m
In Queue
Suspended
IA Status
COD target: 2026
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-15
The proposed project LGE-KU-LGE-GIS-2021-008 is a 500 MW solar and battery hybrid project located in Clark County, Indiana, within the Southeast region. The project, developed by Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU), consists of 500 MW of solar capacity. It is listed in the LGE-KU interconnection queue with an entry date of March 22, 2021, and a proposed commercial operation date of June 15, 2026.
The interconnection status of the project is currently suspended, and its interconnection agreement (IA) status is also listed as suspended. The point of interconnection (POI) is primarily the Trimble County 345 kV bus, with an alternate POI at the Trimble to Speed 345 kV line. The system impact study (SIS) primary was changed to the Trimble to Speed 345 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Clark
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Primary: Trimble County 345 kV bus; Alternate: Trimble to Speed 345 kV line, SIS Primary changed to: Trimble to Speed 345 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- MISO Indiana
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.