LGE-KU-LGE-GIS-2021-018
110 MW hybrid in Bath, KY · In queue since May 2021 · Proposed COD November 2027
110 MW
Capacity
1
Components
Solar
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-30
The proposed project LGE-KU-LGE-GIS-2021-018 is a 110 MW solar and battery hybrid project located in Bath County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). The project consists of 110 MW of solar capacity.
The project is in the LGE-KU interconnection queue, with an entry date of May 1, 2021, and a proposed commercial operation date of November 30, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Spencer Road to Farmers Tap 138 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Bath
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Spencer Road to Farmers Tap 138 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LGE-KU-LGE-GIS-2021-018