LGE-KU-LGE-GIS-2021-020
120 MW hybrid in Mccracken, KY · In queue since June 2021 · Proposed COD December 2023
120 MW
Capacity
1
Components
Solar
4y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 6m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
The proposed project LGE-KU-LGE-GIS-2021-020 is a 120 MW solar and battery hybrid project located in Mccracken County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). The project consists of 120 MW of solar capacity.
The project is currently active in the Louisville Gas & Electric and Kentucky Utilities Energy interconnection queue, with a queue entry date of June 24, 2021, and a proposed commercial operation date of December 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Primary: Grahamville 161 kV bus; Alternate: Grahamville _x0013_ Wickliffe 161 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Mccracken
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Primary: Grahamville 161 kV bus; Alternate: Grahamville _x0013_ Wickliffe 161 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LGE-KU-LGE-GIS-2021-020