LGE-KU-LGE-GIS-2022-002
40 MW generation in Wise, VA · In queue since May 2022 · Proposed COD June 2025
40 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
The proposed LGE-KU-LGE-GIS-2022-002 project is a 40 MW solar generation project located in Wise County, Virginia. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). It is currently active in the LGE-KU interconnection queue, with an entry date of May 2, 2022, and a proposed commercial operation date of June 1, 2025. The point of interconnection is the Dorchester to Blackwood 69 kV line.
The interconnection agreement is currently listed as "In Progress (unknown study)". The project consists of 40 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
VA
County
Wise
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Dorchester to Blackwood 69 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Dominion
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LGE-KU-LGE-GIS-2022-002