LGE-KU-LGE-GIS-2022-0035
660 MW generation in Jefferson, KY · In queue since June 2022 · Proposed COD April 2027
660 MW
Capacity
1
Components
Gas
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
LGE-KU-LGE-GIS-2022-0035 is a proposed 660 MW gas-fired generation project located in Jefferson County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). The project is in the LGE-KU interconnection queue with an entry date of June 21, 2022, and a proposed commercial operation date of April 1, 2027.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Mill Creek Substation 345 kV bus.
Generated from interconnection queue and public data sources
State
KY
County
Jefferson
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Mill Creek Substation 345 kV bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.