LGE-KU-LGE-GIS-2022-007
150 MW hybrid in Lincoln, KY · In queue since September 2022 · Proposed COD October 2026
150 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
LGE-KU-LGE-GIS-2022-007 is a proposed 150 MW hybrid solar and battery project located in Lincoln County, Kentucky. The development project consists of 150 MW of solar capacity. It is listed in the Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU) interconnection queue with a queue entry date of September 6, 2022, and a proposed commercial operation date of October 1, 2026. The interconnection agreement status is listed as "In Progress (unknown study)".
The point of interconnection for the project is the West Garrard _x0013_ Pineville 345 kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
KY
County
Lincoln
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
West Garrard _x0013_ Pineville 345 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.