LGE-KU-LGE-GIS-2022-010
216 MW storage in Bell, KY · In queue since September 2022 · Proposed COD December 2030
216 MW
Capacity
1
Components
Other Storage
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
8y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
LGE-KU-LGE-GIS-2022-010 is a proposed 216 MW battery storage project located in Bell County, Kentucky. The project, categorized as "Other Storage," is being developed within the Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU) service area.
The project is currently active in the LGE-KU interconnection queue, with an entry date of September 30, 2022, and a proposed commercial operation date of December 31, 2030. The interconnection agreement (IA) status is listed as "In Progress (unknown study)." The point of interconnection (POI) is the Pineville - Harlan #1 161 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Bell
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Pineville - Harlan #1 161 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.