LGE-KU-LGE-GIS-2023-0026
660 MW generation in Mercer, KY · In queue since April 2023 · Proposed COD April 2028
660 MW
Capacity
1
Components
Gas
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
The proposed LGE-KU-LGE-GIS-2023-0026 project is a 660 MW gas-fired generation project located in Mercer County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). It is in the Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU) interconnection queue with an entry date of April 14, 2023.
The project's proposed commercial operation date is April 1, 2028. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Brown North Substation 345 kV bus.
Generated from interconnection queue and public data sources
State
KY
County
Mercer
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Brown North Substation 345 kV bus.
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.