LGE-KU-LGE-GIS-2023-004
89 MW hybrid in Mercer, KY · In queue since May 2023 · Proposed COD September 2027
89 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
LGE-KU-LGE-GIS-2023-004 is a proposed 89 MW hybrid solar and battery project located in Mercer County, Kentucky. The project, which consists of 89 MW of solar capacity, is being developed within the Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU) service area.
The project entered the LGE-KU interconnection queue on May 2, 2023, with a proposed commercial operation date of September 1, 2027. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Harrodsburg _x0013_ West Cliff 69 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Mercer
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Harrodsburg _x0013_ West Cliff 69 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LGE-KU-LGE-GIS-2023-004