Project LGE-KU-LGE-GIS-2023-006 — Project Summary

Queue ID
LGE-KU-LGE-GIS-2023-006
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
Daviess, KY
Region
Southeast
Developer
IA Status
In Progress (unknown study)

LGE-KU-LGE-GIS-2023-006

LGE-KU-LGE-GIS-2023-006BetaActiveSolarBatteryLGE-KULBNL

125 MW hybrid in Daviess, KY · In queue since July 2023 · Proposed COD September 2027

125 MW

Capacity

1

Components

Solar

2y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection

Total Duration

4y 2m

In Study38%
Queue EntryJul 24, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

About

LGE-KU-LGE-GIS-2023-006 is a proposed 125 MW hybrid solar and battery project located in Daviess County, Kentucky. The project, under development by Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU), consists of 125 MW of solar capacity. It is currently listed as active in the LGE-KU interconnection queue, with a queue entry date of July 24, 2023, and a proposed commercial operation date of September 1, 2027.

The project's interconnection to the grid is planned at the Zion to Green River Steel 69kV line. The interconnection agreement (IA) status is currently "In Progress (unknown study)". The project has appeared in recent news coverage regarding renewable energy development in the Southeast region.

Generated from interconnection queue and public data sources

Project Details

State

KY

County

Daviess

Grid Region

Southeast

Market

Developer

Utility

Louisville Gas & Electric and Kentucky Utilities Energy

Entity

LGE-KU

Service Type

Point of Interconnection

Zion to Green River Steel 69kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project LGE-KU-LGE-GIS-2023-006