MISO
50 MW generation in Lawrence, MS · In queue since April 2024 · Proposed COD October 2027
50 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
A proposed 50 MW wind energy project is currently in the Midcontinent Independent System Operator (MISO) interconnection queue. Located in Lawrence County, Mississippi, the project entered the queue on April 17, 2024, with a proposed commercial operation date of October 1, 2027. The point of interconnection is GP-Monticello.
The project, identified by queue ID MISO, is listed as an active project in the MISO queue. No developer is specified in the data. There is no indication of an interconnection agreement (IA) being in place, nor is there a match to an existing operating plant in EIA data. There is no indication of recent news coverage.
Generated from interconnection queue and public data sources
State
MS
County
Lawrence
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
GP-Monticello
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- MONTICELLO
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO