MISO-E291
27 MW generation in TX · In queue since May 2012 · Proposed COD January 2016
27 MW
Capacity
1
Components
Hydro
14 years
In Queue
IA Executed
IA Status
COD target: 2016
Total Duration
3y 8m
Schedule
126 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2016-01-01
MISO-E291 is a proposed 27 MW hydroelectric generation project located in Texas and interconnected within the Midcontinent Independent System Operator (MISO) region. The project entered the MISO interconnection queue on May 15, 2012, with a proposed commercial operation date of January 1, 2016. The point of interconnection is the Rich 138 kV substation.
The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
TX
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Rich 138 kV substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- TEXAS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NSP.INVRHL1
- POI Substation
- Rich Valley Substation