MISO-G002
174 MW generation in KY · In queue since December 1998 · Proposed COD January 2016
174 MW
Capacity
1
Components
Coal
27y 5m
In Queue
IA Executed
IA Status
COD target: 2016
Total Duration
17y 1m
Schedule
126 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2016-01-01
The proposed MISO-G002 project is a 174 MW coal-fired generation project located in Kentucky. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on December 1, 1998, with a proposed commercial operation date of January 1, 2016.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is currently listed as unknown.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Unknown
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.