MISO-G017
174 MW generation in KY · In queue since December 1999 · Proposed COD October 2004
174 MW
Capacity
1
Components
Gas
26y 5m
In Queue
IA Executed
IA Status
COD target: 2004
Total Duration
4y 10m
Schedule
263 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2004-10-01
MISO-G017 is a proposed 174 MW gas-fired generation project located in Kentucky. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on December 1, 1999. Its proposed commercial operation date was October 1, 2004, and the project's Interconnection Agreement (IA) has been executed.
The project, sponsored by MISO, consists of 174 MW of gas-fired generation capacity. The point of interconnection (POI) for the project is currently unknown. The project's status is listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Unknown
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.