MISO-G085
7 MW generation in WI · In queue since March 2001 · Proposed COD June 2005
7 MW
Capacity
1
Components
Unknown
25y 2m
In Queue
IA Executed
IA Status
COD target: 2005
Total Duration
4y 3m
Schedule
255 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2005-06-01
The proposed MISO-G085 project is a 7 MW generation project of unknown technology located in Wisconsin. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of March 5, 2001, and a proposed commercial operation date of June 1, 2005. The interconnection agreement (IA) for the project has been executed.
The project consists of a single 7 MW component of unknown type. The point of interconnection (POI) is also unknown. The project's status in the MISO queue is listed as active.
Generated from interconnection queue and public data sources
State
WI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Unknown
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-G085