MISO-G322
10 MW generation in WI · In queue since March 2003 · Proposed COD May 2010
10 MW
Capacity
1
Components
Other
23y 2m
In Queue
IA Executed
IA Status
COD target: 2010
Total Duration
7y 2m
Schedule
194 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2010-05-31
The proposed project MISO-G322 is a 10 MW generation project of unspecified technology located in Wisconsin within the Midcontinent Independent System Operator (MISO) region. The project, sponsored by MISO, was entered into the interconnection queue on March 31, 2003, and has a proposed commercial operation date of May 31, 2010. The point of interconnection is the James St. Substation.
The project's interconnection agreement (IA) has been executed. Recent news coverage of the project is not available.
Generated from interconnection queue and public data sources
State
WI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
James St. Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WPS.PULLIAM31
- POI Substation
- James St