MISO-G326
2 MW generation in WI · In queue since March 2003 · Proposed COD June 2003
2 MW
Capacity
1
Components
Other
23y 2m
In Queue
IA Executed
IA Status
COD target: 2003
Total Duration
3 months
Schedule
279 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2003-06-01
MISO-G326 is a proposed 2 MW generation project of unspecified technology located in Wisconsin. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of March 31, 2003, and a proposed commercial operation date of June 1, 2003. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Crivitz 138kV substation.
The project consists of 2 MW of unspecified generation technology. It is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
WI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Crivitz 138kV
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Crivitz Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-G326