MISO-G346
5 MW generation in MI · In queue since June 2003
5 MW
Capacity
1
Components
Other
22y 11m
In Queue
IA Executed
IA Status
Total Duration
22y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Commercial operation date not yet determined
MISO-G346 is a proposed 5 MW generation project of unspecified technology located in Michigan within the Midcontinent Independent System Operator (MISO) region. The project, sponsored by MISO, entered the MISO interconnection queue on June 1, 2003. The point of interconnection is the Glen Jenks Substation.
The project's interconnection agreement (IA) has been executed, and it remains in active status. The project consists of 5 MW of "Other" generation technology, as categorized in the interconnection queue.
Generated from interconnection queue and public data sources
State
MI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Glen Jenks Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MIUP.MANSTQN1
- POI Substation
- Glen Jenks Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.