MISO-G621
20 MW generation in MN · In queue since April 2006 · Proposed COD December 2018
20 MW
Capacity
1
Components
Wind
20y 1m
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
12y 8m
Schedule
90 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2018-12-01
MISO-G621 is a proposed wind generation project with a total capacity of 20 MW, located in Minnesota within the Midcontinent Independent System Operator (MISO) region. The project consists of 20 MW of wind generation. It entered the MISO interconnection queue on April 18, 2006, with a proposed commercial operation date of December 1, 2018. The interconnection agreement (IA) has been executed.
The point of interconnection (POI) for MISO-G621 is Golf - Wookstock 34.5 kV.
Generated from interconnection queue and public data sources
State
MN
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Golf - Wookstock 34.5 kV
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-G621