MISO-J1844
100 MW storage in Washtenaw, MI · In queue since December 2020 · Proposed COD October 2024
100 MW
Capacity
1
Components
Battery
5y 5m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 10m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-07
MISO-J1844 is a proposed 100 MW battery storage project located in Washtenaw County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of December 31, 2020. The proposed commercial operation date is October 7, 2024. The project's interconnection status is currently in the Cluster Study phase.
The project is being developed within the ITC utility territory and connects to the 19CVTRY point of interconnection. The project consists of a single 100 MW battery component. The project has appeared in recent news coverage regarding energy storage development in the MISO region.
Generated from interconnection queue and public data sources
State
MI
County
Washtenaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
19CVTRY
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1844