MISO-J1863
60 MW storage in Otsego, MI · In queue since August 2021 · Proposed COD September 2024
60 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-15
MISO-J1863 is a proposed 60 MW battery storage project located in Otsego County, Michigan. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO queue on August 16, 2021, with a proposed commercial operation date of September 15, 2024. The interconnecting utility is METC. Its interconnection status is currently in the Cluster Study phase.
The development project consists solely of battery storage, with a total capacity of 60 MW.
Generated from interconnection queue and public data sources
State
MI
County
Otsego
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Vantyle 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.