MISO-J1880
60 MW storage in Ottawa, MI · In queue since August 2021 · Proposed COD September 2024
60 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-15
MISO-J1880 is a proposed 60 MW battery storage project located in Ottawa County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on August 16, 2021. The proposed commercial operation date is September 15, 2024. The project's interconnection agreement status is currently in the Cluster Study phase.
The development project is being proposed within the service territory of METC. The point of interconnection (POI) is the Argenta to Tallmadge 345kV line, 33 miles from Argenta.
Generated from interconnection queue and public data sources
State
MI
County
Ottawa
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Argenta to Tallmadge 345kV (33 miles from Argenta)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1880