MISO-J1882
45 MW storage in Tazewell, IL · In queue since March 2022 · Proposed COD September 2024
45 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-15
MISO-J1882 is a proposed 45 MW battery storage project located in Tazewell County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on March 28, 2022. The proposed commercial operation date is September 15, 2024. Ameren Illinois is the utility associated with the point of interconnection, named San Jose Rail 138kV. The project's interconnection status is currently in the Cluster Study phase.
The development project consists solely of battery storage, with a total capacity of 45 MW. The entity responsible for the project within the MISO queue is MISO itself. The project is listed as active within the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Tazewell
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
San Jose Rail 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1882