MISO-J1894
200 MW storage in Kalamazoo, MI · In queue since October 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 11m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
MISO-J1894 is a proposed 200 MW battery storage project located in Kalamazoo County, Michigan. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO interconnection queue on October 29, 2021, with a proposed commercial operation date of September 30, 2024. The project's interconnection status is currently in the Cluster Study phase.
The development project, which will interconnect at the Jaguar point of interconnection, is sponsored by Michigan Electric Transmission Company (METC). The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
State
MI
County
Kalamazoo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Jaguar
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EES.FORMOSA_BR
- POI Substation
- Jaguar Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1894