MISO-J1898
200 MW storage in Olmsted, MN · In queue since August 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Battery
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
MISO-J1898 is a proposed 200 MW battery storage project located in Olmsted County, Minnesota. The project, under development by Southern Minnesota Municipal Power Agency, entered the MISO interconnection queue on August 13, 2021. Its proposed commercial operation date is September 30, 2024.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Byron 161 kV substation. The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
State
MN
County
Olmsted
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY
Entity
MISO
Service Type
—
Point of Interconnection
Byron 161 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Byron Substation