MISO-J1900
200 MW storage in Wayne, MI · In queue since August 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
The proposed MISO-J1900 project is a 200 MW battery storage development in Wayne County, Michigan. Interconnecting to ITC via the Brownstown 12 120kV point of interconnection, the project entered the MISO interconnection queue on August 13, 2021. Its proposed commercial operation date is September 30, 2024, and its interconnection status is currently in the Cluster Study phase.
The project consists solely of battery storage, with a total capacity of 200 MW. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MI
County
Wayne
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Brownstown 12 120kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Brownstown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1900