MISO-J1902
200 MW storage in Wayne, MI · In queue since August 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
MISO-J1902 is a proposed 200 MW battery storage project located in Wayne County, Michigan. The project, which consists entirely of battery storage, is in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is August 13, 2021, with a proposed commercial operation date of September 30, 2024. The project's interconnection status is currently in the Cluster Study phase.
The project is interconnected with ITC and is listed in the MISO queue. No developer is specified in the queue data. The point of interconnection (POI) is the Ironton 120 kV substation. The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
State
MI
County
Wayne
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
IRONTON 120 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Ironton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1902