MISO-J1914
150 MW generation in Presque Isle, MI · In queue since October 2023 · Proposed COD November 2023
150 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
1 month
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
MISO-J1914 is a proposed solar generation project with a total capacity of 150 MW, located in Presque Isle County, Michigan. The project is being developed within the Midcontinent Independent System Operator (MISO) region and interconnected with the Rockport-Port calcite 138kV Transmission line.
The project entered the MISO interconnection queue on October 5, 2023, with a proposed commercial operation date of November 1, 2023. Its interconnection status is currently in the Cluster Study phase. The utility involved is METC.
Generated from interconnection queue and public data sources
State
MI
County
Presque Isle
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Rockport-Port calcite 138kV Transmission line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1914