MISO-J1917
200 MW generation in Livingston, MI · In queue since August 2021 · Proposed COD November 2023
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
MISO-J1917 is a proposed 200 MW solar generation project located in Livingston County, Michigan. The project, which interconnects with ITC, entered the MISO interconnection queue on August 19, 2021. Its proposed commercial operation date is November 1, 2023. The project's interconnection status is currently in the Cluster Study phase.
The proposed project consists of 200 MW of solar photovoltaic generation. Its point of interconnection is the Madrid-Majestic 345 kV line.
Generated from interconnection queue and public data sources
State
MI
County
Livingston
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Madrid- Majestic 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1917