MISO-J1918
132 MW generation in Montcalm, MI · In queue since August 2021 · Proposed COD November 2023
132 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
The proposed MISO-J1918 project is a 132 MW solar generation project located in Montcalm County, Michigan. The project, interconnected within the Midcontinent Independent System Operator (MISO) queue, entered the queue on August 24, 2021, with a proposed commercial operation date of November 1, 2023. The project's interconnection status is currently in the Cluster Study phase.
The project is being developed within the service territory of METC and connects to the Nelson Road-Kenowa 345kV Transmission Line.
Generated from interconnection queue and public data sources
State
MI
County
Montcalm
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Nelson Road-Kenowa 345kV Transmission Line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1918