MISO-J1932
100 MW generation in Gladwin, MI · In queue since August 2021 · Proposed COD October 2024
100 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
MISO-J1932 is a proposed solar generation project with a total capacity of 100 MW, located in Gladwin County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on August 24, 2021. Its proposed commercial operation date is October 1, 2024. The project's interconnection agreement status is currently in the Cluster Study phase.
The project, interconnected with Michigan Electric Transmission Company (METC), consists of 100 MW of solar photovoltaic generation. The project is listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Gladwin
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1932