MISO-J1934
150 MW storage in Kenosha, WI · In queue since August 2021 · Proposed COD October 2025
150 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
4y 2m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
MISO-J1934 is a proposed 150 MW battery storage project located in Kenosha County, Wisconsin. The project, which interconnects to the American Transmission Company via the Lakeview 138kV point of interconnection, entered the MISO interconnection queue on August 24, 2021. Its proposed commercial operation date is October 1, 2025. The project's interconnection status is currently in the Cluster Study phase.
The development project consists solely of battery storage, with a total capacity of 150 MW. The project is listed in the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
WI
County
Kenosha
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Lakeview 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Lakeview Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J1934