MISO-J1943
200 MW generation in Columbia, WI · In queue since August 2021 · Proposed COD October 2024
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
The proposed MISO-J1943 project is a 200 MW solar generation facility located in Columbia County, Wisconsin. The project, which consists of 200 MW of solar photovoltaic generation, is in the MISO interconnection queue as of August 23, 2021, with a proposed commercial operation date of October 1, 2024. The interconnection point of the project is the N Madison - Columbia 345kV substation. Its interconnection status is currently in the Cluster Study phase.
The project is in the queue of American Transmission Company, under the oversight of MISO. No developer is listed in the queue data. The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
WI
County
Columbia
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
N Madison - Columbia 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Madison