MISO-J1944
200 MW generation in Sanilac, MI · In queue since August 2021 · Proposed COD November 2023
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-01
MISO-J1944 is a proposed solar generation project located in Sanilac County, Michigan, with a total capacity of 200 MW. The project, interconnected with ITC, entered the MISO queue on August 23, 2021, and has a proposed commercial operation date of November 1, 2023. Its interconnection status is currently in the Cluster Study phase.
The development project consists of 200 MW of solar photovoltaic generation. It is listed in the MISO interconnection queue.
Generated from interconnection queue and public data sources
State
MI
County
Sanilac
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Banner-Rapson 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.