MISO-J1967
150 MW generation in Champaign, IL · In queue since March 2022 · Proposed COD October 2025
150 MW
Capacity
1
Components
Wind
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-01
MISO-J1967 is a proposed 150 MW wind generation project located in Champaign County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 24, 2022. The proposed commercial operation date is October 1, 2025. The interconnecting utility is Ameren Illinois, and the point of interconnection is Rantoul East 138kV. The project's interconnection status is currently in the Cluster Study phase.
The development project consists of 150 MW of wind generation capacity. The project is listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
Champaign
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Rantoul East 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.