MISO-J2001
220 MW generation in Newaygo, MI · In queue since August 2021 · Proposed COD May 2025
220 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-01
The proposed MISO-J2001 project is a 220 MW solar generation facility located in Newaygo County, Michigan. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on August 16, 2021, with a proposed commercial operation date of May 1, 2025. The interconnecting utility is METC. As of the latest data, the project's interconnection status is in the Cluster Study phase.
The project consists of 220 MW of solar photovoltaic generation. The point of interconnection (POI) is the Ludington to Kenowa 345kV line.
Generated from interconnection queue and public data sources
State
MI
County
Newaygo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Ludington to Kenowa 345kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2001