MISO-J2029
62.5 MW generation in Marquette, MI · In queue since November 2021 · Proposed COD September 2024
62.5 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 10m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
MISO-J2029 is a proposed solar generation project with a total capacity of 62.5 MW, located in Marquette County, Michigan. The project is in the MISO interconnection queue, having entered on November 30, 2021. Its proposed commercial operation date is September 1, 2024. The interconnecting utility is American Transmission Company. The project's interconnection status is currently in the Cluster Study phase.
The development project consists of 62.5 MW of solar photovoltaic generation. It is located at the Point of Interconnection (POI) of the Perch Lake Substation.
Generated from interconnection queue and public data sources
State
MI
County
Marquette
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Perch Lake Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Perch Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.