MISO-J2033
200 MW generation in Clay, IL · In queue since August 2021 · Proposed COD April 2024
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 8m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-04-15
MISO-J2033 is a proposed 200 MW solar generation project located in Clay County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an original queue entry date of August 26, 2021. The proposed commercial operation date is April 15, 2024. The interconnection status is currently in the Cluster Study phase.
The project, which is located within the Ameren Illinois service area, consists of 200 MW of solar photovoltaic generation. The point of interconnection (POI) is at the 7XENIA - 7MTVERNW 345.0kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Clay
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7XENIA - 7MTVERNW 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2033