MISO-J2045
50 MW storage in Newton, IN · In queue since March 2022 · Proposed COD September 2024
50 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
The proposed MISO-J2045 project is a 50 MW battery storage development in Newton County, Indiana. Interconnection was requested by Northern Indiana Public Service Company in the MISO queue on March 28, 2022, with a proposed commercial operation date of September 30, 2024.
The project is currently in the Cluster Study phase of the interconnection process. The point of interconnection is the Goodland 138 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
Newton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Goodland 138 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2045