MISO-J2049
200 MW generation in Macon, IL · In queue since March 2022 · Proposed COD September 2025
200 MW
Capacity
1
Components
Wind
4y 2m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
MISO-J2049 is a proposed 200 MW wind generation project located in Macon County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 25, 2022. The proposed commercial operation date is September 1, 2025. The project's interconnection status is currently in the Cluster Study phase.
The project, which is being developed within the Ameren Illinois utility territory, consists of 200 MW of wind generation capacity.
Generated from interconnection queue and public data sources
State
IL
County
Macon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.