MISO-J2068
75 MW generation in Pierce, WI · In queue since July 2021 · Proposed COD November 2024
75 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
MISO-J2068 is a proposed solar generation project located in Pierce County, Wisconsin, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 75 MW, consists entirely of solar photovoltaic technology. Northern States Power Company is the utility associated with the project.
The project entered the MISO interconnection queue on July 19, 2021, and has a proposed commercial operation date of November 30, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Herbert 69 kV Substation.
Generated from interconnection queue and public data sources
State
WI
County
Pierce
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Herbert 69 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2068