MISO-J2069
100 MW hybrid in Montcalm, MI · In queue since November 2021 · Proposed COD September 2024
100 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 10m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
MISO-J2069 is a proposed 100 MW hybrid solar and battery energy storage project located in Montcalm County, Michigan. The project, interconnecting with ITC, entered the MISO interconnection queue on November 30, 2021, with a proposed commercial operation date of September 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The development project consists of 100 MW of solar generation capacity coupled with battery storage. It is listed in the MISO queue under queue ID MISO-J2069.
Generated from interconnection queue and public data sources
State
MI
County
Montcalm
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Eureka - Vestaburg 138kV Transmission Line (J1379 POI)
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2069