MISO-J2078
200 MW generation in Story, IA · In queue since August 2021 · Proposed COD June 2025
200 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
MISO-J2078 is a proposed solar generation project with a total capacity of 200 MW. The project is located in Story County, Iowa, and is interconnected within the Midcontinent Independent System Operator (MISO) region. The interconnection request was entered into the MISO queue on August 13, 2021, with a proposed commercial operation date of June 30, 2025.
The project's interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Fernald Substation, and the interconnecting utility is ITC Midwest.
Generated from interconnection queue and public data sources
State
IA
County
Story
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
—
Point of Interconnection
Fernald Substation
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Fernald Substation