Project MISO-J2080 — Project Summary

Queue ID
MISO-J2080
Capacity
200 MW
Technology
Wind
Status
active
Location
Oliver, ND
Region
MISO
Developer
IA Status
In Progress (unknown study)

MISO-J2080

MISO-J2080BetaActiveWindMISOLBNL + Live

200 MW generation in Oliver, ND · In queue since August 2021 · Proposed COD May 2024

200 MW

Capacity

1

Components

Wind

4y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

2y 9m

Schedule

24 months past proposed COD

In Study38%
Queue EntryAug 12, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-01

About

The proposed MISO-J2080 project is a 200 MW wind generation facility located in Oliver County, North Dakota. The project, which consists of 200 MW of wind capacity, is being developed within the Midcontinent Independent System Operator (MISO) region. Minnesota Power Inc. is the interconnecting utility.

The project entered the MISO interconnection queue on August 12, 2021, with a proposed commercial operation date of May 1, 2024. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Square Butte East 230 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

ND

County

Oliver

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

MINNESOTA POWER INC.

Entity

MISO

Service Type

Point of Interconnection

Square Butte East 230 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J2080