MISO-J2087
125 MW generation in Renville, MN · In queue since July 2021 · Proposed COD November 2024
125 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-30
MISO-J2087 is a proposed 125 MW solar generation project located in Renville County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of July 19, 2021. The proposed commercial operation date is November 30, 2024. Northern States Power Company is the interconnecting utility.
The interconnection agreement for MISO-J2087 is currently listed as "In Progress (unknown study)". The point of interconnection is the Franklin 115kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
MN
County
Renville
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Franklin 115kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Franklin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2087