MISO-J2098
309 MW generation in Calhoun, MI · In queue since August 2021 · Proposed COD March 2025
309 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Cluster Study
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-31
MISO-J2098 is a proposed solar generation project with a total capacity of 309 MW located in Calhoun County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on August 22, 2021. The proposed commercial operation date is March 31, 2025. The project's interconnection agreement status is currently in the Cluster Study phase.
The project, interconnected to the BATTLE CREEK - ONEIDA 345.0kV point of interconnection, is being developed within the Michigan Electric Transmission Company (METC) service area.
Generated from interconnection queue and public data sources
State
MI
County
Calhoun
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
BATTLE CREEK - ONEIDA 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2098