MISO-J2099
399.03 MW generation in Portage, WI · In queue since June 2022 · Proposed COD October 2024
399.03 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
2y 4m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
The proposed MISO-J2099 project is a 399.03 MW solar generation project located in Portage County, Wisconsin. The project entered the MISO interconnection queue on June 22, 2022, with a proposed commercial operation date of October 1, 2024. The interconnection request is currently in the Cluster Study phase.
The project is interconnected to the American Transmission Company via the Rocky Run to Werner West 345 kV line.
Generated from interconnection queue and public data sources
State
WI
County
Portage
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Rocky Run to Werner West 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J2099