550 MW generation in Redwood, MN · In queue since August 2021 · Proposed COD September 2024
550 MW
Capacity
1
Components
Wind
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 1m
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-01
The proposed MISO-J2104 project is a 550 MW wind generation facility located in Redwood County, Minnesota. The project is being developed within the Northern States Power Company utility territory. It entered the MISO interconnection queue on August 4, 2021, with a proposed commercial operation date of September 1, 2024.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Lyon County 345 kV - Cedar Mountain 345 kV line.
Generated from interconnection queue and public data sources
State
MN
County
Redwood
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Lyon County 345 kV - Cedar Mountain 345 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.